Mechanical infrastructure for demanding data center environments, with a focus on high-capacity cooling and coordinated system installation.

Representative data center mechanical infrastructure
BARSTOW, TX
DATA CENTER CONFIDENTIAL CLIENT
DATA CENTER / MECHANICAL SYSTEMS

MAF-1 Buildings 1 & 3 — Confidential Client

A 12-month mechanical installation across two buildings within a four-building data center development in Barstow, Texas.

The MAF-1 development includes four 53,000-square-foot data center buildings. Severn completed its work on Buildings 1 and 3 over a 12-month period.

The HVAC scope included two chilled-water piping loops with a total of 20,172 tons of cooling capacity across 40 chillers, supported by 24 computer room air handling (CRAH) units.

Two air handling units (AHUs) and two outside air handling units (OAHUs) provided 20,800 CFM of airflow. The system also included three expansion tanks, two glycol makeup systems, and 40 buffer tanks with a capacity of 3,000 gallons each.

20,172Tons of Cooling
40Chillers
24CRAH Units
12Months

Texas

(filler text) From Smithsonian collection vaults to hyperscale data halls, The Severn Group designs, installs, and commissions the mechanical and plumbing systems that keep the Washington, DC, and Northern Virginia region’s most demanding buildings running.